Priorities and approximate timelines
- Update use agreements with Federal Bureau of Investigation; Clark County Sheriff’s Office; Bureau of Alcohol, Tobacco, Firearms, and Explosives; and Metro Explosives Disposal Unit
- Quarter 2, 2025
- Improve access control security at the Camp Bonneville main gate
- Quarter 1, 2025
- Support Washington Department of Ecology in finalizing the draft periodic review for presentation to the community
- Quarter 3, 2025
- Complete a fence repair and upgrade project near Livingston Mountain quarry
- Quarter 2, 2025
- Maintain and repair fence
- Ongoing
- Open bid for road maintenance pilot project, for construction services for maintenance of several miles of general access roads at Camp Bonneville
- Quarter 2, 2025 (notice to contractors)
- Plan shaded fuel break: mapping and layout of shaded fuel break units prioritizing portions of west, north, and south boundaries for brush removal and timber sale
- Quarters 2 and 3, 2025
- Support Washington Department of Ecology in finalizing the Remedial Investigation/Feasibility Study for Remedial Action Unit 2c or Landfill 4/Sitewide Groundwater
- Quarters 3 and 4, 2025